Final Phase II Addendum & RAO for the Former Bird Machine Co. Site

The PDFs listed below include: 1) a transmittal letter, 2) the Final Phase II Comprehensive Site Assessment (CSA) Addendum for the Demolition Debris Area, and 3) the Final Response Action Outcome (RAO) for RTN 4-3024222 at the Former Bird Machine Co. Site. The attached reports include responses to public comments on the draft versions, which were the subject of our public meeting at Town Hall on 12/6/11. The comments and responses appear in appendices of each document.

December 6, 2011 Public Meeting

Presentation Given at December 6th Meeting

AMEC and Baker Hughes Inc. will present a summary of the Public Comment Draft of the Phase II Comprehensive Site Assessment (CSA) Addendum and the Response Action Outcome (RAO) Statement for the Bird Machine Company Site on Tuesday, December 6, 2011 at 7:00 PM in the Main Meeting Room at the Town Hall.

The public comment period for the Draft CSA Addendum and Draft RAO Statement will begin on November 16, 2011 and will extend through December 12, 2011. Comments can be submitted to Chris Clodfelter of Baker Hughes at the following address:

Chris Clodfelter Senior HS&E Specialist
Baker Hughes Incorporated
2929 Allen Parkway Suite 2100
Houston, Texas 77019-2118

Office: 713.439.8329 | Fax: 713.439.8383

Copies of the Draft CSA Addendum and Draft RAO Statement will be available at the MassDEP Southeast Regional Office (File Review Telephone Number: 508-946-2718) and at the Walpole Public Library (Telephone Number: 508-660-7341) or may be download from the links below. A copy of the executive summary of the Draft CSA Addendum, which summarizes the findings and conclusions presented in the document, is attached to transmittal letter (also below).

October 25, 2011 Public Meeting

AMEC and Baker Hughes Inc. will present a summary of the Draft Remedial Action Plan (RAP) and be available to answer questions on the document. The RAP will be in the Walpole Town Library and the MassDEP public information repositories by October 6. You can also download it here.

August 16, 2011 Public Meeting

There will be a Public Meeting on August 16, 2001 to discuss Draft of the Phase II Comprehensive Site Assessment (CSA) for the Bird Machine Company Site, Release Tracking Number (RTN) 4-3024222, 7:00 PM in the Main Meeting Room at the Town Hall August 16, 2011 Presentation

September 3 Public Hearing Cancelled

This notice is to inform you of the cancellation of the 3 September 2008 Zoning Board of Appeals public hearing regarding the Demolition Debris Area Site Zoning Board Special Permit Request – Non-Residential filling of greater than 150 cubic yards. The Special Permit Request, dated 25 July 2008, has been withdrawn at the request of Baker Process, Inc. Full Notice

Meeting Notice

Presentation of Phase II Comprehensive Site Assessment Report and Phase III Remedial Action Plan for Demolition Debris Area, RTN 4-3024105 on Tuesday, September 25, 2007 at 7:00 PM in the Senior Center at the Town Hall

Meeting Notice

Report by Baker Hughes on Wednesday, February 21, 2007 at 7:00 PM in the Main Meeting Room at the Town Hall Presentation by Baker Hughes